VIDEO: Time lapse of Highline High’s construction progress; tennis courts moved to Sunnydale

Despite strict work requirements during the COVID-19 pandemic, construction progress continues at the Highline High School site, thanks to construction workers.

The new school is expected to open in September 2021.

Below is a time-lapse video showing the new Highline High School being installed, courtesy of Highline Public Schools:

DISTRICT CONSTRUCTION PROGRESS REPORT:

    • Steelwork continues, with steel in place up to roof level in several areas. Work on the steel studs for the walls has begun.
    • The “filling”, or completion of the last piece of the structural steel skeleton, will take place this summer.
    • The foundation and concrete slab work is 85% complete.
    • Raised concrete slab work is underway and 87% complete.
    • Structural steelwork continues. Structural steel is in place up to roof level in several areas of the building. Roof decking is being installed.
    • The installation of the concrete masonry units (CMU) blocks for the auxiliary gymnasium and the main gymnasium are 100% complete.
    • The installation of the CMU blocks for the physical education area is approximately 99% complete.
    • The installation of the CMU blocks for the auditorium/theater is estimated to be 45% complete.
    • The installation of mechanical equipment for heating, ventilation and air conditioning (HVAC) is estimated to be 10% complete.
    • The electrical installation is estimated at 10% complete.
    • Deep utility works are approximately 95% complete.
    • Storm water connection work on South 152nd Street is underway.
    • The water district connection is completed.
    • Sewer connections, sidewalks and crosswalks are underway and are estimated to be 40% complete.
    • Metal roof decking (no finished roof with standing metal seams) and roof insulation work is estimated to be 40% complete.
    • Work on the steel stud walls has also started throughout the project and is expected to be 20% complete.
    • Work is underway at the Sunnydale site to install site utilities in support of the installation of the new tennis court and restrooms. The grading and storm drainage work is 95% complete.

TENNIS COURTS MOVED TO SUNNYDALE SITE

As part of the new Highline High School replacement project, six new tennis courts are being built on part of the Sunnydale site grounds.

Architects and district staff had to get creative with where to build tennis courts when designing the new high school within the tight constraints of the existing site.

Here’s the bonus to the construction of tennis courts at the nearby Sunnydale site: we expect the new tennis courts to be completed this summer and available for the 2020-21 tennis season. A small bathroom building is included in the project.

The existing large play toy in Sunnydale remains in place, along with the ball diamond on the south side of the Sunnydale field. The tennis courts are on the north side of the Sunnydale course. The new courts are located off South 156th Street and across from the Moshier Park grounds.

A new pedestrian light was installed by the City of Burien at the south 156th Street exit of HHS and Moshier Field. After the new Highline High School opens in the fall of 2021, student-athletes accessing the new tennis courts will use the crosswalk and traffic lights.

VIDEO: Time lapse of Highline High's construction progress;  tennis courts moved to Sunnydale 2

View of the new HHS Tennis Court construction area on the north side of the field at the Sunnydale site.

VIDEO: Time lapse of Highline High's construction progress;  tennis courts moved to Sunnydale 3

View of the southeast corner of the new HHS across South 156th Street and Moshier Field. Photographed from the tennis court construction area at the Sunnydale site.

Photos/video courtesy of Highline Public Schools